DIAMOND HOUSE– CONSTRUCTION COST BREAKDOWN.

– CONSTRUCTION COST BREAKDOWN.     DIAMOND HOUSE BY WWW.A4ARCHITECT.COM     APPROXIMATE COSTS PER SUB-PHASE  AMMOUNT -LOW COST FINISHES  AMMOUNT -MIDDLE COST FINISHES  AMMOUNT -HIGH COST FINISHES   1…

– CONSTRUCTION COST BREAKDOWN.

 

 

DIAMOND HOUSE BY WWW.A4ARCHITECT.COM

 

 

APPROXIMATE COSTS PER SUB-PHASE

 AMMOUNT -LOW COST FINISHES

 AMMOUNT -MIDDLE COST FINISHES

 AMMOUNT -HIGH COST FINISHES

 

1

Substructures[Foundations]      216,766.44        324,198.93        431,631.42

 

2

Reinforced Concrete Frame[Ring beam]       79,252.80        118,531.60        157,810.40

 

3

Superstructure walling-masonry stone       99,181.82        148,337.73        197,493.63

 

4

Roof structure, covering, finishes and rainwater goods-GCI roofing sheets       86,453.04        129,300.38        172,147.72

 

5

Windows-louvre       44,505.60          66,563.20          88,620.80

 

6

Doors       64,642.56          96,680.32        128,718.08

 

7

External finishes       29,986.56          44,848.32          59,710.08

 

8

Floor Finishes-cement screed       12,289.20          18,379.90          24,470.60

 

9

Wall Finishes-plaster on paint       42,408.00          63,426.00          84,444.00

 

10

Ceiling Finishes       50,789.28          75,961.16        101,133.04

 

11

Sanitary Fittings       34,108.80          51,013.60          67,918.40

 

12

project management       34,627.50          51,789.38          68,951.25

 

13

Septic tank, Electrical Wiring,Plumbing      165,300.00        247,225.00        329,150.00

 

 

Sub Total    960,311.60   1,436,255.51   1,912,199.42

 

CONSTRUCTION SUPERVSION       24,007.79          35,906.39          47,804.99

 

 

 

Total Estimate    984,319.39   1,472,161.90   1,960,004.41

 

 