Bedsitter Earthbag Unit. Kes 129,000
The cost of constructing a complete bedsitter eathbag unit is estimated at kes 129,000.
The cost of constructing the unit without the windows, doors, internal bathroom and kitchenette is kes 89,000
MAIN SUMMARY | ||||
Substructures | 13,350.00 | |||
Superstructure walling | 15,000.00 | |||
Roof structure, covering, finishes and rainwater goods | – | |||
Windows | 8,800.00 | |||
Doors | 13,460.00 | |||
External finishes | 30,000.00 | |||
Floor Finishes | 1,500.00 | |||
Wall Finishes | 30,000.00 | |||
Ceiling Finishes | – | |||
Sanitary Fittings | 17,400.00 | |||
Prime Cost and Provisional sums | – | |||
Sub Total | 129,510.00 | |||
Allow for Preliminaries | – | |||
Total Estimate | 129,510.00 | |||
39,660.00 | ||||
Estimate minus Ceiling,Sanitary,doors, windows | 89,850.00 |
This unit is suitable for backyard extension to the main House as a Servants Quarters, or as a hotel resort accommodation room unit.
The design is based on the Cameroonian traditional Musgum houses which have lasted for over 1000 years to date.
The Musgum houses have been able to withstand the forces of nature for thousands of years . The science behind this architecture has been used to come up with the Kenyan Earthbag house units .
www.a4architect.com provides architectural design and construction project management to completion for this type of building.
3 Bedroomed Earthbag Unit. Kes 760,000
The concept behind the Musgum Cameroonian architecture has been used to come up with the 3 bedroomed earthbag house.
The estimated cost of construction for the complete 3 bedroomed unit is kes 760,000.
The estimated cost of constructing the 3 bedroomed unit without the fittings, doors and windows is kes 560,000
MAIN SUMMARY | |||||
1 | Substructures | 61,440.00 | |||
3 | Superstructure walling | 83,480.00 | |||
4 | Roof structure, covering, finishes and rainwater goods | 92,050.00 | |||
5 | Windows | 33,200.00 | |||
6 | Doors | 62,835.00 | |||
7 | External finishes | 158,500.00 | |||
8 | Floor Finishes | 13,000.00 | |||
9 | Wall Finishes | 158,500.00 | |||
10 | Ceiling Finishes | 63,180.00 | |||
12 | Sanitary Fittings | 36,700.00 | |||
14 | Prime Cost and Provisional sums | – | |||
Sub Total | 762,885.00 | ||||
Allow for Preliminaries | – | ||||
Total Estimate | 762,885.00 | ||||
195,915.00 | |||||
Estimate minus Ceiling,Sanitary,doors, windows | 566,970.00 |
The Earthbag house concept saves cost through use of local materials, use of ingenious structural engineering support systems and use of wall material for roofing.