– CONSTRUCTION COST BREAKDOWN.
|
DIAMOND HOUSE BY WWW.A4ARCHITECT.COM |
|||
|
||||
|
|
|||
|
APPROXIMATE COSTS PER SUB-PHASE |
AMMOUNT -LOW COST FINISHES |
AMMOUNT -MIDDLE COST FINISHES |
AMMOUNT -HIGH COST FINISHES |
|
||||
1 |
Substructures[Foundations] | 216,766.44 | 324,198.93 | 431,631.42 |
|
||||
2 |
Reinforced Concrete Frame[Ring beam] | 79,252.80 | 118,531.60 | 157,810.40 |
|
||||
3 |
Superstructure walling-masonry stone | 99,181.82 | 148,337.73 | 197,493.63 |
|
||||
4 |
Roof structure, covering, finishes and rainwater goods-GCI roofing sheets | 86,453.04 | 129,300.38 | 172,147.72 |
|
||||
5 |
Windows-louvre | 44,505.60 | 66,563.20 | 88,620.80 |
|
||||
6 |
Doors | 64,642.56 | 96,680.32 | 128,718.08 |
|
||||
7 |
External finishes | 29,986.56 | 44,848.32 | 59,710.08 |
|
||||
8 |
Floor Finishes-cement screed | 12,289.20 | 18,379.90 | 24,470.60 |
|
||||
9 |
Wall Finishes-plaster on paint | 42,408.00 | 63,426.00 | 84,444.00 |
|
||||
10 |
Ceiling Finishes | 50,789.28 | 75,961.16 | 101,133.04 |
|
||||
11 |
Sanitary Fittings | 34,108.80 | 51,013.60 | 67,918.40 |
|
||||
12 |
project management | 34,627.50 | 51,789.38 | 68,951.25 |
|
||||
13 |
Septic tank, Electrical Wiring,Plumbing | 165,300.00 | 247,225.00 | 329,150.00 |
|
||||
|
||||
|
Sub Total | 960,311.60 | 1,436,255.51 | 1,912,199.42 |
|
||||
|
CONSTRUCTION SUPERVSION | 24,007.79 | 35,906.39 | 47,804.99 |
|
||||
|
||||
|
||||
|
Total Estimate | 984,319.39 | 1,472,161.90 | 1,960,004.41 |
|