HOTEL AT AMBOSELI
ESTIMATED COST OF CONSTRUCTION
Reception, offices, and Lounge: Approximately 300m2. Estimated cost of construction including consultancy fees: KES 15,000,000.
Bar: Approximately 100m2: Estimated cost of construction including consultancy fees: KES 5,000,000.00.
Restaurant: Approximately 100m2: Estimated cost of construction including consultancy fees: KES 5,000,000.00.
Kitchen: Approximately 100m2: Estimated cost of construction including consultancy fees: KES 5,000,000.00.
20 Bandas: Approximately 50m2 each: Estimated cost of construction including consultancy fees: KES 50,000,000.00.
TOTAL: KES 80,000,000.00
Architect Francis Gichuhi Kamau